How Long Does a Custom Kitchen Really Take? A Triad Renovation Timeline

From first measure to final drawer pull — a realistic week-by-week look at a custom kitchen build in Winston-Salem, Greensboro, or Durham.

·5 min read·NC Cabinet Design

The most common question we get on a first call isn't about price — it's about time. Here's what a real custom kitchen project looks like from the moment you call us to the day you cook the first meal.

Weeks 1–2: Consultation and measure

We visit your home, understand how you cook, and take a full field measure. Nothing is designed yet — we're gathering.

Weeks 3–5: Design and material selection

You'll see elevations, 3D renderings, and physical samples of wood species and finishes. This is where most of the meaningful decisions get made — and where slowing down saves you from regret later.

Weeks 6–10: Shop build

Once the design is signed off, cabinets are built in our Yadkinville workshop. Solid wood face frames, dovetailed drawers, hand-applied finish. Lead time depends on wood species (walnut runs longer than maple) and finish complexity.

Weeks 11–12: Install

The same team that built the cabinets installs them. A standard kitchen installs in 4 to 7 working days. Countertop templating happens at day 2 of install; stone typically returns 10 to 14 days later.

Total: 12 to 16 weeks from first call to first meal

If someone promises you 6 weeks, they're either using stock cabinets or cutting corners on finish. A properly built and finished custom kitchen simply takes time — and the timeline is the reason it lasts.

Get in touch

Ready to Transform Your Space?

Not ready for a full quote? Use the form to send us a message or ask a question. We respond personally — no call centers, no automated runaround.

Call the shop

336-244-0251

Visit the workshop

6458 Service Rd
Yadkinville, NC 27055

Quick replyLocal NC craft